Mechanical & Electrical Installation Works @ United Utilities Ellesmere Port & Oldham WwTW

 Edwards Elite Engineering were asked to fabricate & install new process water, fuel gas, oil and exhaust pipework along with steelwork platforms to gain access to a newly installed carbon filter and 2 x Jenbacher 320 containerised engines @ United Utilities Ellesmere Port & Oldham Waste Water Treatment Plants. Edwards Elite were also asked to sub contract out and manage the installation and testing of the high & low voltage electrical services and associated earthing.

Engine Build

Edwards Elite had to supply labour to assist with a contract lift on assembling both of 320 Jenbacher containeriesed engines and installing all the roof mounted equipment & pipework. Labour was also supplied to position all main items of equipment such as the Carbon Filters, Boosters, Chiller, Oil Tanks and Water Pumps etc...

 

Design

Edwards Elite were asked to supply the following design work:

1) Design and Calculations for the Engine Container Access Platform to BS5950

2) Design and Calculations for the Carbon Filters Access Platform to BS5950

3) Design and Calculations for the Gas, Water and Oil Pipework including Pipe Supports

 

Fabrication & Installation Works

The works required the use of our coded welders to fabricate the pipework, supports and access platforms. Skilled EEE Ltd operatives were on site to install the fabricated materials by operating multiple types of lifting equipment/machinery from SL10 Genie lIfts & Telescopic Handlers to running 35 Tonne Contract Crane Lifts

 

   